St. Michael’s Centre
Situated near Imperial Wharf in Fulham, the project saves a disused youth centre from demolition, creating nine new homes and a children’s nursery through refurbishment and extension.
-
Client
WP Development
-
Architect
Wimshurt Pelleriti
-
Photography
Jon Reid
-
Value
£4m
-
Size
1,150m²
-
Completion
2024
The original intention to demolish the five-storey structure, which had fallen into disrepair, was set aside following the acquisition of the site by the architect, Wimshurt Pelleriti. The brief shifted to a more sustainable, low carbon design that retains as much of the existing building as possible. Our structural approach was central to that change, with early optioneering and analysis proving how the existing masonry façade could be retained and reused structurally. This new strategy was achieved, in part, by the repurposing of the church masonry façade into a loadbearing element to support new timber internal floors. Our team were responsible for the structural and civil aspects of the design, including the temporary works required for the façade.
Timber was identified as the best solution for the upper floors, with its lightweight properties minimising the load on the façade and existing foundations. Timber floor joists are supported by primary Kerto members which are continuous over a central line of timber columns and span to the masonry piers at the perimeter. By splicing the LVL beams at points of contraflexure, we achieved continuous spans with reduced deflections and a shallower structural zone, helping to stay within the building’s height limits while also cutting material use. Balconies are formed by steel frames with timber infill, which are tied back to the new walls of the side extensions.
The façade was a key challenge. It had never been intended to take vertical loads from multiple new floors, so we carried out an extensive suite of investigations including brick strength and water absorption testing, chemical and petrographic analysis of the mortar and bricks, and soils testing of the existing foundations. This gave us the design values to prove the piers could act as loadbearing elements rather than relying on new foundations. We worked with the design team and contractor on the development of a construction sequence that maintained the stability of the façade throughout. A bespoke temporary works strategy propped the façade while the entire internal structure was removed and rebuilt, with phasing adjusted on site as conditions were uncovered.
The project brings the characterful youth centre back into use, preserving its historic façade while creating new homes and community infrastructure within the neighbourhood.
Awards
-
2025
Structural Awards
Shortlisted
More